Water treatment
Mkhizwana Water Treatment Works upgrade
Early-stage engineering and design review for the upgrade of a 1.3 Ml/day treatment works in KwaZulu-Natal.
Client environmentuMngeni-uThukela Water programme
Appointment routeHCE appointment through Ingérop South Africa
LocationMkhizwana, KwaZulu-Natal
Delivery periodCommenced January 2023 • Completed
1.3 Ml/dayTreatment capacity stated in the reference
R58.3mRecorded project value, including VAT
1–3ECSA stage coverage
01 • Client requirement
The outcome the commission required.
The commission required the design basis and developing solution to be tested early enough for recommendations to improve the final design before downstream delivery.
02 • HCE appointment
Defined scope. Controlled attribution.
Undertake Stage 1–3 professional services and design review for the treatment-works upgrade.
03 • Engineering response
Technical input connected to delivery.
- Reviewed the Stage 1–3 engineering information and design development.
- Applied water-infrastructure judgement to the proposed solution and interfaces.
- Issued technical recommendations directed at final-design quality.
04 • Verified delivery outcome
What the source record confirms.
- The signed company reference confirms that all requirements were completed professionally and effectively.
- The reference specifically records that HCE recommendations improved final-design quality.
- Successful completion was confirmed to the satisfaction of the appointing consultant.